U.S. Bank (Vikings) Stadium

Park Construction Company paved the U.S. Bank Stadium floor prior to the placement of the turf. Most commonly associated with ensuring proper grading and paving of airport runways and highway projects, 3D control systems were used in the grading and paving process. Park Construction’s Caterpillar 160M motor grader and AP1055E paver were equipped with 3D…

Carver Elementary in Maplewood

Park Construction was awarded the Site work, Utilities, Asphalt Paving, and Building Demolition package for the Carver Elementary School additions and renovations project in Maplewood, MN. This project included the demolition of a 24,000 SF existing wing of an elementary school and the construction of two new additions, three new parking lots, a bus/parent drop-off loop, and a new playground area.